N2 Ashbourne Bypass / M50 Junction
| Local Authority: | Meath County Council |
| Start County: | Dublin |
| End County: | Meath |
| Description: | The scheme involved the construction of approximately 3.5 km of new dual three lane carriageway with hard shoulder, approximately 13.5 km of new dual two lane carriageway with hard shoulder and 1.5 km of new dual two lane carriageway without hard shoulder. The scheme also included 16 bridge structures, two grade separated interchanges, four at-grade roundabouts and approximately 6 km of minor road works. The scheme was progressed as a Design and Build contract and was officially opened by An Taoiseach, Bertie Ahern T.D., on 25th May 2006.
This project has been funded by the Irish Government under the National Development Plan and Transport 21 and by the European Union from the European Regional Development Fund. |
| Mainline Length (km): | 17 |
| Contractor: | Jons Sisk JV |
| Current Project Phase: | Complete |
| Scheme Website: | http://www.n2finglasashbourne.ie |